Photo of JOCO Culvert

The 2013-2014 group's project is close to this one, so they took some photos of the completed construction.

Thursday, April 25, 2013

more progress on JOCO culvert construction



From: Root, Wes, PWK
Sent: Thursday, April 25, 2013 3:48 PM
To:
Subject: RE: Culvert D.00-6.78

They have cleared and grubbed within the construction limits. Excavation of the old structure should begin in the next few weeks.

Thanks,
                 Wes

Monday, March 18, 2013

2012 JOCO Culvert in construction

The rural culvert replacement designed by John Blancett's group in 2012 is under construction.  If you go down there and take any photos, send some to Dr. O'Bannon.  Congratulations!  Your work is being implemented.

Monday, April 30, 2012

Culvert replacement in rural Johnson County, KS

Client:  Johnson County Public Works, KS

Team:  Wade Bennett, Kevin Buck, William Carpenter, Alex McCaskill, Adam O'Kane, Isaac Somogie, Dan Sparks (PM), Nick Steele

Practitioner/coach:  John Blancett, P.E.

Drainage improvements for 105th St & Cherokee, Leawood KS

Client:  City of Leawood, KS

Team:  Nathan Grahl, Kingsley Kantanka, Daniel Mann, Tyler Myers (PM), Diego Rojas, Antonio Saavedra, Kevin Thomas, Christy Wilson

Practitioner/coach:  Mark Montgomery, P.E.

Cedar Niles and Santa Fe intersection improvement, Gardner KS

Client:  City of Gardner, KS

Team:  Bashar El Ella, Kyle Dunning, Ryan Harbaugh, Jacob Herzog, David Petree, Jessica Sturgess (PM), Dzevad Tahirovic, Nathan Wood

Practitioner/coach:  Curt Mader, P.E.

Wednesday, November 9, 2011

MODOT Ribbon-cutting on US 50 intersection improvements

MODOT marked the occasion of its collaboration with UMKC Red Cone by hosting a ribbon-cutting at Route F and US50 in Jackson County.  Both Katie Horner (student project manager) and Dean Kevin Truman delivered remarks at the event.  It was well-attended with students from the design groups, representatives of elected officials, and MODOT personnel.